Live GMAT classes with Target Test Prep start Nov 21 and Nov 22. First class free.

See classes
Target Test Prep · GMAT

Choose how you want to prepare

Learn live with an expert or move at your own pace. Every option includes the complete TTP study system.

Newsweek Readers’ Choice Awards 2026 winner: Target Test Prep, #1 Test Prep

Target Test Prep was voted #1 Best Test Prep in the 2026 Newsweek Readers’ Choice™ Awards.

★★★★★5.0563 reviews
GMATLiveTeachStarts Nov 22
Josh Braslow, Target Test Prep GMAT expert
LIVE ONLINE CLASSES

Get Ready for GMAT Test Day Faster with Live Online Classes

with Josh Braslow, 20+ years in test prep

Nov 22 · Josh Braslow
Sun · 9:30 AM to 12:30 PM ET
Included
40 hours of live online classes + 6 months of TTP OnDemand
  • Attend the first class for free
  • Every class is recorded, so you never fall behind
View classes & enroll
Limited seats availableTarget Test Prep
EALiveTeachOnDemandStart anytime
EXECUTIVE ASSESSMENT

Target Test Prep EA OnDemand

Self-paced EA prep. Study on your schedule.

EXECUTIVE ASSESSMENT

with

165+ EA score guarantee
$05-day trial no automatic billing
Schedule
Included
40 hours of live online classes plus six months of access to the complete TTP EA OnDemand course.
  • 165+ EA Score Guarantee
  • 4,100+ Quant, Verbal, and Integrated Reasoning practice questions
  • 400+ hours of in-depth video lessons
  • 3,000+ step-by-step video solutions
View EA class & enroll Start free 5-day trial
Limited cohort · enrollment openTrial includes full course accessTarget Test Prep
GMATOnDemandStart anytime
SELF-PACED MASTERCLASS

Target Test Prep GMAT OnDemand

Complete access from day one. Study on your schedule.

715+ score guarantee
$0to start then $127/mo
  • Personalized study plan and analytics
  • Thousands of lessons and practice questions

A factory has two machines. Machine X can produce 200 pins p

Expert replies
by Max@Math Revolution » Mon Jun 24, 2019 12:08 am
Timer
00:00
Your answer
Difficulty–

right wrong

Pick an answer to see how members did

[GMAT math practice question]

A factory has two machines. Machine X can produce 200 pins per hour and machine Y can produce 500 pins per hour. At least one machine is in operation throughout the 8-hour work day. The factory must produce 5,000 pins every day. What is the least possible number of hours that machines X and Y must work together on each day?

A. 4
B. 5
C. 6
D. 7
E. 8
Join the discussion
Source: — Problem Solving |

by Max@Math Revolution » Tue Jun 25, 2019 11:52 pm
=>

In order to minimize the number of hours that the two machines work together, the more efficient machine Y should work for the entire day.
Thus, Y works for 8 hours and produces 8 * 500 = 4,000 pins.
There are 1,000 pins remaining for machine X to produce. This takes 1,000/200 = 5 hours.

Therefore, B is the answer.
Answer: B