GMATPrep - Work

by NDLadyzman » Tue Sep 16, 2008 9:54 am
Hey guys,

Can anyone show me how to go about solving this work problem? Thanks!!!
Attachments
Work.doc
(55.5 KiB) Downloaded 124 times

Legendary Member
Posts: 829
Joined: Mon Jul 07, 2008 10:09 pm
Location: INDIA
Thanked: 84 times
Followed by:3 members

Re: GMATPrep - Work

by sudhir3127 » Tue Sep 16, 2008 10:04 am
NDLadyzman wrote:Hey guys,

Can anyone show me how to go about solving this work problem? Thanks!!!
i go with 3

total work done by 6 machine in 12 days is 6*12 = 72
to complete the same amount of work

let the additional machines be X

(6+x) *8 = 72

X = 3

hope that helps...

Junior | Next Rank: 30 Posts
Posts: 21
Joined: Mon Feb 26, 2007 11:42 am

Hi

by NDLadyzman » Tue Sep 16, 2008 10:20 am
Yes got it. Thank you very much, sir.

Legendary Member
Posts: 891
Joined: Sat Aug 16, 2008 4:21 am
Thanked: 27 times
Followed by:1 members
GMAT Score:660(

by 4meonly » Wed Sep 17, 2008 8:54 am
Rate of one machine is 1/72

(1/72)*8(days)*x(machines)=1
x=9
9-6=3