Time and Work Problem.

by karthik.sharma » Mon Jul 12, 2010 2:35 am
4 Men and 3 Women can finish a job in 6 days.5 Men and 7 Women can finish the same job in 4 days.How long will 1 man and 1 woman take to finish the job.?

a) 22(2/7) days
b) 25 (1/2) days
c) 5 (1/7) days
d) 12 (7/22) days.

How do you solve such a problem?

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 1179
Joined: Sun Apr 11, 2010 9:07 pm
Location: Milpitas, CA
Thanked: 447 times
Followed by:88 members

by Rahul@gurome » Mon Jul 12, 2010 2:52 am
One day work of (4M + 3W) is 1/6. So, the 1st equation is 4M + 3W = 1/6
One day work of (5M + 7W) is 1/4. So, the 2nd equation is 5M + 7W = 1/4
Solving the equations by elimination method, we get W = 1/78 and M = 5/156
So, one day work of 1W + 1M = 1/78 + 5/156 = 7/156
Therefore, 1 man and 1 woman would take 156/7 or 22(2/7) days to finish the job.

[spoiler]The correct answer is (A).[/spoiler]
Rahul Lakhani
Quant Expert
Gurome, Inc.
https://www.GuroMe.com
On MBA sabbatical (at ISB) for 2011-12 - will stay active as time permits
1-800-566-4043 (USA)
+91-99201 32411 (India)

Legendary Member
Posts: 2326
Joined: Mon Jul 28, 2008 3:54 am
Thanked: 173 times
Followed by:2 members
GMAT Score:710

by gmatmachoman » Mon Jul 12, 2010 3:30 am
Rahul@gurome wrote:One day work of (4M + 3W) is 1/6. So, the 1st equation is 4M + 3W = 1/6
One day work of (5M + 7W) is 1/4. So, the 2nd equation is 5M + 7W = 1/4
Solving the equations by elimination method, we get W = 1/78 and M = 5/156
So, one day work of 1W + 1M = 1/78 + 5/156 = 7/156
Therefore, 1 man and 1 woman would take 156/7 or 22(2/7) days to finish the job.

[spoiler]The correct answer is (A).[/spoiler]
Rahul, seems a bit of calculation is invloved..will this much calculation is necessary in GMAT ?? Will these types pop up?

Legendary Member
Posts: 537
Joined: Fri Jan 22, 2010 10:06 pm
Thanked: 14 times
Followed by:1 members

by frank1 » Mon Jul 12, 2010 3:31 am
Rahul@gurome wrote:One day work of (4M + 3W) is 1/6. So, the 1st equation is 4M + 3W = 1/6
One day work of (5M + 7W) is 1/4. So, the 2nd equation is 5M + 7W = 1/4
Solving the equations by elimination method, we get W = 1/78 and M = 5/156
So, one day work of 1W + 1M = 1/78 + 5/156 = 7/156
Therefore, 1 man and 1 woman would take 156/7 or 22(2/7) days to finish the job.

[spoiler]The correct answer is (A).[/spoiler]
thanks
lol i was panicking for nothing...and was trying to solve it with arithmetic only....and was making problem unnecessarily big....
introduction of alzebra turned it into very simple problem...
may be this is good gmat question

thanks
GMAT score is equally counted as your GPA and 78 clicks can change you life.