Time and work problem

This topic has expert replies
Master | Next Rank: 500 Posts
Posts: 127
Joined: Mon May 11, 2009 10:04 am
Thanked: 5 times

Time and work problem

by apex231 » Sat Jul 02, 2011 6:14 pm
A wall has to be completed in 50 days by employing 50 workers. After 25 days only 40% of the work is complete. How many more men are needed to complete the work on time?

Answer is 25

The approach that I followed is -
Let the total work = 50 * 50 = 2500 man days
Work remaining after 25 days = 2500 * 60 / 100 = 1500 man days
Total men required to complete remaining work in next 25 days = 1500/25 = 60
Extra men required = 60 - 50 = 10.

Where am I going wrong?

Senior | Next Rank: 100 Posts
Posts: 34
Joined: Thu Jun 30, 2011 4:15 am
Thanked: 1 times
Followed by:1 members

by ntamhane » Sat Jul 02, 2011 7:36 pm
Hi apex,
I approached the sum in the following way:
After 25days 60% of the work is remaining
Worker days Work
50 25 0.4
50+x 25 0.6

0.6*25*50=(50+x)*25*0.4

x=25

Senior | Next Rank: 100 Posts
Posts: 52
Joined: Wed May 18, 2011 8:48 pm
Thanked: 4 times

by newgmattest » Tue Jul 05, 2011 1:03 am
Hi GMAT Experts,

Can someone help here.

Thanks.

User avatar
Junior | Next Rank: 30 Posts
Posts: 24
Joined: Mon May 31, 2010 3:29 am
Location: Hyderabad
Thanked: 2 times

by casperkamal » Tue Jul 05, 2011 9:28 am
I did it this way..

if 50 people work for 25 days then total work done is 1250 days

this is 40% So 100% 3125 days.

since 1250 days are already complete the remaining days of work to be done is 3125-1250 = 1875

So 1875/25 is 75 men. 50 already employed so 25 to be employed.
Kamal

User avatar
Junior | Next Rank: 30 Posts
Posts: 24
Joined: Mon May 31, 2010 3:29 am
Location: Hyderabad
Thanked: 2 times

by casperkamal » Tue Jul 05, 2011 9:34 am
Where am I going wrong?
I'm still not very sure. But you can check this. A wall that needs to be completed in 50 days by 50 workers doesn't indicate that it is 2500 man days work.

start from the later point where you say if 50 people work for 25 days then they complete 40% of the work. So it is 1250 days of work.
Kamal

Junior | Next Rank: 30 Posts
Posts: 21
Joined: Sun Jun 05, 2011 10:39 pm
Thanked: 2 times
Followed by:1 members

by worldpeace93 » Tue Jul 05, 2011 9:47 am
apex231 wrote:A wall has to be completed in 50 days by employing 50 workers. After 25 days only 40% of the work is complete. How many more men are needed to complete the work on time?

Answer is 25

The approach that I followed is -
Let the total work = 50 * 50 = 2500 man days
Work remaining after 25 days = 2500 * 60 / 100 = 1500 man days
Total men required to complete remaining work in next 25 days = 1500/25 = 60
Extra men required = 60 - 50 = 10.

Where am I going wrong?


You are wrong in taking total work = 2500
You have to take it as 40% of work = 25X50
hence remaining work =WR= (60/40)*25X 50
No of men = WR/25=75

hence answer is 25men

Senior | Next Rank: 100 Posts
Posts: 41
Joined: Mon Jan 10, 2011 4:54 pm
Thanked: 1 times

by Buix0065 » Tue Jul 05, 2011 8:37 pm
Hi,

My approach.

There is 100 units of work needed to be done.

50 workers, over 25 days accomplishes 40 units.

In another 25 days, the 50 workers will accomplish another 40.

you need another 20 units completed in that time, which is half of what 50 workers can do, so 50/2 = 25 more workers.

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Tue Jul 05, 2011 9:07 pm
A wall has to be completed in 50 days by employing 50 workers. After 25 days only 40% of the work is complete. How many more men are needed to complete the work on time?
Since 40% of the work is completed in the first 25 days, 60% must be completed in the remaining 25 days.
Thus, 60-40 = 20 more units must be completed in the remaining 25 days than were completed in the first 25 days.
We need to determine how many workers are needed to complete these 20 additional units.
Since 50 workers can complete 40 units, the number of workers needed to complete 20 units = 25.
The approach that I followed is -
Let the total work = 50 * 50 = 2500 man days
The values above do not satisfy the situation described in the problem.
Although 50 workers are hired to build the wall in 50 days, this number of workers is insufficient: 50 workers can complete only 40% of the wall in 25 days.
If we conclude that work = workers*days = 50*50 = 2500 units, then 50 workers will complete half of the wall in 25 days.

To use this approach:
Let rate per worker = 1 unit per day.
Work completed by 50 workers each day = 50*1 = 50 units.
Work completed over 25 days = 25*50 = 1250 units.

Let w = wall.
Since 1250 units = 40% of the wall:
1250 = .4w
w = 1250/.4 = 3125 units.

Remaining work after 25 days = 3125-1250 = 1875 units.
To be completed in 25 days, number of units each day = 1875/25 = 75.
Since each worker completes 1 unit per day, 75 total workers are needed.
Thus, 75-50 = 25 additional workers are needed.
Last edited by GMATGuruNY on Wed Jul 06, 2011 10:34 am, edited 2 times in total.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

User avatar
Master | Next Rank: 500 Posts
Posts: 461
Joined: Tue May 10, 2011 9:09 am
Location: pune
Thanked: 36 times
Followed by:3 members

by amit2k9 » Tue Jul 05, 2011 9:24 pm
man hours for 25 days = 25*50 = 1250 (estimated) But actual = 1000.
total man hours required = 50*50 = 2500

thus in 25 days balance man hours = 2500-1000 = 1500

hence 1500/25 = 60.

hence 60-50 = 10 more men required.
For Understanding Sustainability,Green Businesses and Social Entrepreneurship visit -https://aamthoughts.blocked/
(Featured Best Green Site Worldwide-https://bloggers.com/green/popular/page2)

Legendary Member
Posts: 1119
Joined: Fri May 07, 2010 8:50 am
Thanked: 29 times
Followed by:3 members

by diebeatsthegmat » Wed Jul 06, 2011 6:47 pm
GMATGuruNY wrote:
A wall has to be completed in 50 days by employing 50 workers. After 25 days only 40% of the work is complete. How many more men are needed to complete the work on time?
Since 40% of the work is completed in the first 25 days, 60% must be completed in the remaining 25 days.
Thus, 60-40 = 20 more units must be completed in the remaining 25 days than were completed in the first 25 days.
We need to determine how many workers are needed to complete these 20 additional units.
Since 50 workers can complete 40 units, the number of workers needed to complete 20 units = 25.
The approach that I followed is -
Let the total work = 50 * 50 = 2500 man days
The values above do not satisfy the situation described in the problem.
Although 50 workers are hired to build the wall in 50 days, this number of workers is insufficient: 50 workers can complete only 40% of the wall in 25 days.
If we conclude that work = workers*days = 50*50 = 2500 units, then 50 workers will complete half of the wall in 25 days.

To use this approach:
Let rate per worker = 1 unit per day.
Work completed by 50 workers each day = 50*1 = 50 units.
Work completed over 25 days = 25*50 = 1250 units.

Let w = wall.
Since 1250 units = 40% of the wall:
1250 = .4w
w = 1250/.4 = 3125 units.

Remaining work after 25 days = 3125-1250 = 1875 units.
To be completed in 25 days, number of units each day = 1875/25 = 75.
Since each worker completes 1 unit per day, 75 total workers are needed.
Thus, 75-50 = 25 additional workers are needed.
hi,
can you please tell me if i do this math correctly?
50 workers do 0.4 job in 25 days
x worker do 0.6 job in 25 days so x=75
so we need 25 more workers to finish the work on time.
can i logically do that? or the solution is wrong?