Six machined work at a constant rate and do a job in 12 days. If I want to do the job in 8 days, how many extra workers do I need?

2, 3, 4, 6, or 8

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Tue Mar 22, 2016 12:17 am
Six machines, each working at the same constant rate, together can complete a certain job in 12 days. How many additional machines, each working at the same constant rate, will be needed to complete the job in 8 days?

2
3
4
6
8
Approach 1: Plug in a rate for EACH MACHINE

Let the rate for each machine = 1 unit per day.
Rate for 6 machines = 6 units per day.
In 12 days, the amount of work produced by 6 machines = r*t = 6*12 = 72 units.
To produce 72 units in 8 days, the required amount of work per day = w/t = 72/8 = 9 units per day.
To increase the rate from 6 units per day to 9 units per day, 3 more machines are needed.

The correct answer is B.

Approach 2: Inverse proportion method

The number of machines is INVERSELY PROPORTIONAL to the number of days:
(machines)(days) = (machines)(days).
As the number of machines INCREASES, the number of days must DECREASE, so that in each case the SAME AMOUNT OF WORK is produced.

Since 6 machines take 12 days, and the job is to be completed in 8 days, we get:
6 * 12 = m * 8
72 = 8m
m = 9.

Since 9 machines are required, the original number of machines -- 6 -- must increase by 3.

The correct answer is B.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3