Machines A and B each produce tablets at their respective constant rates. Machine A has produced 30 tablets when Machine B is turned on. Both machines continue to run until Machine B's total production catches up to Machine A's total production. How many tablets does Machine A produce in the time that it takes Machine B to catch up?

(1) Machine A's rate is twice the difference between the rates of the two machines.

(2) The sum of Machine A's rate and Machine B's rate is five times the difference between the two rates.


The answer provided is D; Its posted in BTG itself (answered by GMATGuruNY also):

https://www.beatthegmat.com/machines-a-a ... 70314.html

If you approach this question with the concept of relative speed, I get this way:
Tablets = Distance (miles)
Rate (tablets per hour) = Speed (miles per hour)
A: Rate (speed) of machine A.
B: Rate (speed) of machine B.
B > A;


Relative Speed = (Speed of B) - (Speed of A) = (0.5*A);
(this can be derived from (1) and (2) independently)


Time (B catches up with A)
= (Extra Distance/Relative Speed)
= (30+x)/(0.5* A)

I think that the solution provided ignores the number of tablets that A produces after B is turned on. In that case, the numerator of the time to meet will be: (30+x) where x is the number of tablets that A will produce after B is turned on. So, for B to catch up A, B will have to produce 30 (that A already produced) plus x (that A will produce after B is turned on).

I think the answer should be E. Please let me know if I am wrong.

User avatar
Legendary Member
Posts: 2131
Joined: Mon Feb 03, 2014 9:26 am
Location: https://martymurraycoaching.com/
Thanked: 955 times
Followed by:140 members
GMAT Score:800

by MartyMurray » Fri Feb 26, 2016 5:55 am
If B can catch up to A, then B must be faster than A.

Using that information, translate the statements exactly.

(1) Machine A's rate is twice the difference between the rates of the two machines.

A = 2(B - A)

A = 2B - 2A

3A = 2B

A = (2/3)B

Since we know that A = (2/3)B, we can calculate how many tablets each will make when the other makes a certain number.

For instance, in the time it takes for B to make 30 tablets, A will make 20.

Every time A makes a 2 tablets, B will make 3, which is 1 more than A makes. So they need to do that 30 times for B to make 30 more tablets than A makes and to thus catch up.

So in catching up B will make 90 tablets while A makes 60.

You don't actually have to do the math though. You just need to realize that the production of one can be determined given the production of the other.

Sufficient.

(2) The sum of Machine A's rate and Machine B's rate is five times the difference between the two rates.

A + B = 5(B - A)

A + B = 5B - 5A

6A = 4B

A = (2/3)B

Sufficient.

The correct answer is D.
Marty Murray
Perfect Scoring Tutor With Over a Decade of Experience
MartyMurrayCoaching.com
Contact me at [email protected] for a free consultation.

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Fri Feb 26, 2016 7:26 am
s777 wrote:Relative Speed = (Speed of B) - (Speed of A) = (0.5*A)
The expression in red is incorrect.
B - A ≠ 0.5A.

An algebraic approach to Statement 1:
Machine A's rate is twice the difference between the rates of the two machines.

A = 2(B-A)
A = 2B - 2A
3A = 2B
B = (3/2)A.

Let t = the time for B to catch up.
Work produced by A in t hours = At.
Since B = (3/2)A, work produced by B in t hours = Bt = (3/2)(At).

At the end of the t hours, A's work = B's work.
But BEFORE the t hours begin, A has already produced 30 tablets.
Implication:
During the t hours, A produces 30 fewer tablets than B.

Since A's work in t hours is equal to 30 less than B's work in t hours, we get:
At = (3/2)At - 30
30 = (1/2)(At)
60 = At.
Thus, the work produced by A in t hours = 60 tablets.
SUFFICIENT.
Last edited by GMATGuruNY on Mon Feb 29, 2016 3:37 am, edited 1 time in total.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

Newbie | Next Rank: 10 Posts
Posts: 8
Joined: Thu Dec 22, 2011 9:34 am

by s777 » Sun Feb 28, 2016 8:59 pm
Hello Guru,

Thanks very much for the clarity on this topic. I now understand that I cannot use Relative Speed concept in Work-Time questions. I really appreciate your help.

Just wanted to clarify something in your post; there are a couple of typos:

At the end of t hours, A's work = B's work.
But BEFORE the t hours begin, A (not B) has already produced 30 tablets.
Implication:
During the t hours that A (and B ofcourse) works, A (not B) produces 30 fewer tablets than B (not A).


Since A's (not B's) work in t hours is equal to 30 less than B's (not A's) work in t hours, we get:


(3/2)(At) = At + 30 (no minus sign)
30 = (1/2)(At)
60 = At.

But the concept is absolutely fine. Thanks very much.

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Mon Feb 29, 2016 3:41 am
s777 wrote:Hello Guru,

Thanks very much for the clarity on this topic. I now understand that I cannot use Relative Speed concept in Work-Time questions. I really appreciate your help.

Just wanted to clarify something in your post; there are a couple of typos:
Good catch.
I've amended my solution as follows:

Let t = the time for B to catch up.
Work produced by A in t hours = At.
Since B = (3/2)A, work produced by B in t hours = Bt = (3/2)(At).

At the end of the t hours, A's work = B's work.
But BEFORE the t hours begin, A has already produced 30 tablets.
Implication:
During the t hours, A produces 30 fewer tablets than B.

Since A's work in t hours is equal to 30 less than B's work in t hours, we get:
At = (3/2)At - 30
30 = (1/2)(At)
60 = At.
Thus, the work produced by A in t hours = 60 tablets.
SUFFICIENT.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3