A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?
14
13
11
9
7
pl explain...
source-gmatclub.
word problem...
This topic has expert replies
-
- Legendary Member
- Posts: 1337
- Joined: Sat Dec 27, 2008 6:29 pm
- Thanked: 127 times
- Followed by:10 members
find # days (must be integer value)advita wrote:A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?
14
13
11
9
7
pl explain...
source-gmatclub.
(1/24 + 1/30 + 1/48 + 1/60)D=1 => D=240/27 => D=~8.8 or 9 (integer value)
IOM D 9
- anshumishra
- Legendary Member
- Posts: 543
- Joined: Tue Jun 15, 2010 7:01 pm
- Thanked: 147 times
- Followed by:3 members
One days Job for machine A and B = 3/2*(1/24+1/30) = 9/80advita wrote:A furniture manufacturer has two machines, but only one can be used at a time. Machine A is utilized during the first shift and Machine B during the second shift, while both work half of the third shift. If Machine A can do the job in 12 days working two shifts and Machine B can do the job in 15 days working two shifts, how many days will it take to do the job with the current work schedule?
14
13
11
9
7
pl explain...
source-gmatclub.
Hence no. of days = 80/9 = 9.