A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into12 equal monthly

This topic has expert replies
Legendary Member
Posts: 1622
Joined: Thu Mar 01, 2018 7:22 am
Followed by:2 members

Timer

00:00

Your Answer

A

B

C

D

E

Global Stats

A project scheduled to be carried out over a single fiscal year has a budget of $12,600, divided into12 equal monthly allocations. At the end of the fourth month of that fiscal year, the total amount actually spent on the project was $4,580. By how much was the project over its budget?

(A) $380
(B) $540
(C) $1,050
(D) $1,380
(E) $1,430

Answer: A

Source: Official Guide