C’s share of the earnings

by sanju09 » Tue Apr 05, 2011 3:57 am
A, B and C, each of them working alone can complete a job in 6, 8 and 12 days respectively. If all three of them work together to complete a job and earn $2340, what will be C's share of the earnings?
(A) $520
(B) $630
(C) $1000
(D) $1080
(E) $1170
The mind is everything. What you think you become. -Lord Buddha



Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001

www.manyagroup.com

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 3835
Joined: Fri Apr 02, 2010 10:00 pm
Location: Milpitas, CA
Thanked: 1854 times
Followed by:523 members
GMAT Score:770

by Anurag@Gurome » Tue Apr 05, 2011 4:05 am
sanju09 wrote:A, B and C, each of them working alone can complete a job in 6, 8 and 12 days respectively. If all three of them work together to complete a job and earn $2340, what will be C's share of the earnings?
(A) $520
(B) $630
(C) $1000
(D) $1080
(E) $1170
1 day work of A, B, and C is 1/6, 1/8, and 1/12 respectively.
This means A:B:C = 1/6:1/8:1/12
LCM of 6, 8, 12 = 24
So, A:B:C = 24/6:24/8:24/12 = 4:3:2
Hence, 4x + 3x + 2x = 2340
9x = 2340 implies x = $260, which implies C's share = 2 * $260 = $520

The correct answer is A.
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)

Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/

User avatar
Legendary Member
Posts: 965
Joined: Thu Jan 28, 2010 12:52 am
Thanked: 156 times
Followed by:34 members
GMAT Score:720

by vineeshp » Tue Apr 05, 2011 4:07 am
A 520.

Working together, they finish 3/8 ( = 1/6 + 1/8 + 1/12) of work in one day. Or in other words, they can finish the work in 8/3 days.

This means when they work together, each machine works for 8/3 days. C working at speed of 1/12 finishes 8/3 * 1/12 = 2/9 of the total work.

So money earned = 2/9 * 2340 = 520.