Machine A can complete a certain job in x hours. Machine B can complete the same job in y hours. If A and B work together at their respective rates to complete the job, which of the following represents the fraction of
the job that B will not have to complete because of A's help?
A. (x - y)/ (x + y)
B. x / (y - x)
C. (x + y) / xy
D. y / (x - y)
E. y / (x + y)
This question seems like Greek to me. Not even able to start. Please help.
Work Rate Problem - 4
This topic has expert replies
- GMATGuruNY
- GMAT Instructor
- Posts: 15539
- Joined: Tue May 25, 2010 12:04 pm
- Location: New York, NY
- Thanked: 13060 times
- Followed by:1906 members
- GMAT Score:790
Let the job = 10 units.Machine A can complete a certain job in x hours. Machine B can complete the same job in y hours. If A and B work together at their respective rates to complete the job, which of the following represents the fraction of the job that B will not have to complete?
(x - y)/(x + y)
x/(y - x)
(x + y)/xy
y/(x - y)
y/(x + y)
Let x = 5 hours.
Rate for A alone = w/t = 10/5 = 2 units per hour.
Let y = 2 hours.
Rate for B alone = w/t = 10/2 = 5 units per hour.
The combined rate for A+B = 2+5 = 7 units per hour.
Of the 7 units produced each hour, 2 will produced by A and 5 will be produced by B.
Thus, the fraction of the job produced by A = 2/7. This is our target.
Now we plug x=5 and y=2 into the answers to see which yields our target of 2/7.
A quick scan of the answers reveals that only E works:
y/(x+y) = 2/(5+2) = 2/7.
The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
-
- GMAT Instructor
- Posts: 2630
- Joined: Wed Sep 12, 2012 3:32 pm
- Location: East Bay all the way
- Thanked: 625 times
- Followed by:119 members
- GMAT Score:780
Work = Rate * Time
We're only doing one job, so Work = 1. If Machine A did the job alone, we know
Work = Rate * Time
1 = Rate * x
1/x = Rate
If Machine B did the job alone, we know
Work = Rate * Time
1 = Rate * y
1/y = Rate
So we have each Machine's rate per hour: A's is 1/x, B's is 1/y.
If they work together, we have
Work = Rate * Time
1 = (1/x + 1/y) * Time
xy/(x + y) = Time
Each machine works for the same amount of time. The fraction that A does is
A's Rate * A's Time =>
(1/x) * xy/(x+y) =>
y/(x + y)
so our answer is E.
We're only doing one job, so Work = 1. If Machine A did the job alone, we know
Work = Rate * Time
1 = Rate * x
1/x = Rate
If Machine B did the job alone, we know
Work = Rate * Time
1 = Rate * y
1/y = Rate
So we have each Machine's rate per hour: A's is 1/x, B's is 1/y.
If they work together, we have
Work = Rate * Time
1 = (1/x + 1/y) * Time
xy/(x + y) = Time
Each machine works for the same amount of time. The fraction that A does is
A's Rate * A's Time =>
(1/x) * xy/(x+y) =>
y/(x + y)
so our answer is E.