In the Porter Toy company, the average time required for each of the n production workers to assemble a trainset is t minutes. If all the workers work fulltime how many hours of plant operations will be required to fill an order for 5000 of these train sets?
A) 5000t/60n
B)5000(60)/nt
C)5000nt/60
D)5000(60n)/t
E)60nt/5000

OA: A

User avatar
Community Manager
Posts: 1537
Joined: Mon Aug 10, 2009 6:10 pm
Thanked: 653 times
Followed by:252 members

by papgust » Sun Jul 04, 2010 10:30 pm
You could use basic logic here instead of going for calculations.

Firstly, the given time taken to assemble a trainset is t minutes. Question asks for the total time in hours. So, you need to divide by 60 and not multiply by 60. Eliminate B, D, and E.

We need to choose b/w A and C. If only 1 worker assembles 5000 trainsets, the total time taken will be 5000*t/60 hrs. If there are n workers, then divide 5000*t/60 hrs by n. It's 5000*t / 60*n hours.
Download GMAT Math and CR questions with Solutions from Instructors and High-scorers:
https://www.beatthegmat.com/download-gma ... 59366.html

-----------

GO GREEN..! GO VEG..!

Daily Quote:
"Stop feeling sorry for the Butcher if you had to go Veg. The butcher can find another job but the poor animal cannot get back its life"

Master | Next Rank: 500 Posts
Posts: 250
Joined: Thu Jan 07, 2010 2:21 am
Thanked: 10 times

by saurabhmahajan » Mon Jul 05, 2010 1:14 am
one doubt.

the problem says about average time.so the total time to assemble one trainset will be nt.so assembling 5000 sets would be 5000nt.
assume 10 people require average 5 min to assemble one set then total time required is 50 min.so 5000 sets would be 5000*50....right?

and sinced asked in hour so divide by 60

therefore i went for option 5000nt/60.

Please correct me.
Thanks and regards,
Saurabh Mahajan

I can understand you not winning,but i will not forgive you for not trying.

Master | Next Rank: 500 Posts
Posts: 161
Joined: Mon Apr 05, 2010 9:06 am
Location: Mumbai
Thanked: 37 times

by 4GMAT_Mumbai » Mon Jul 05, 2010 1:19 am
saurabhmahajan wrote:one doubt.

the problem says about average time.so the total time to assemble one trainset will be nt.

Please correct me.
Hi,

I am afraid the flaw lies in this initial assumption. If there are 3 people who take an average of 5 minutes each to construct a train set, will we say that the total time to assemble one train set is 5 * 3 = 15 minutes ? Hence, the expression nt does not make much sense.

Hope this helps. Thanks.
Naveenan Ramachandran