Work machines
This topic has expert replies
-
- Legendary Member
- Posts: 966
- Joined: Sat Jan 02, 2010 8:06 am
- Thanked: 230 times
- Followed by:21 members
Machine hours = 6*12 = 72.
Now if work has to be done in 8 days, x*8=72
x=9.
Therefore 3 more machines are needed
Now if work has to be done in 8 days, x*8=72
x=9.
Therefore 3 more machines are needed
- Abhishek009
- Master | Next Rank: 500 Posts
- Posts: 359
- Joined: Wed Mar 11, 2009 4:37 am
- Location: Kolkata, India
- Thanked: 50 times
- Followed by:2 members
We knowrnaah wrote:It takes 12 days for 6 machines working together at their respective rates to complete a job. How many more machines will be needed to reduce the number of days from 12 to 8 days?
Work = Time taken * No of workers
here it is given It takes 12 days for 6 machines to complete a job.
so the total work can be found out as 12 * 6 = 72 units
Now we have found out the total work and we are required to find out the No of workers when timme taken reduces to 8 units...
again we go thru the same formula :
Work = Time taken * No of workers
72 = 8 * No of workers
So , 9 = No of workers
Abhishek
Just Different way of doing It, once if you understand this logic behind a kind of problem then it would be very easy for you. Try this
6 Machines in 12 Days completes 1 piece of work
1 Machine in 12 Days completes 1/6 of work
1 Machine in 1 Day completes 1/6*12 = 1/72 of work
Which means
Machines * Days * rate (Rate per day per machine) = 1
So, let us say number of new Machines = x
then, x * 8 * 1/72 = 1
x*8 = 72
x = 9
Answer = 9 - 6 = 3
Thanks,
SVD
6 Machines in 12 Days completes 1 piece of work
1 Machine in 12 Days completes 1/6 of work
1 Machine in 1 Day completes 1/6*12 = 1/72 of work
Which means
Machines * Days * rate (Rate per day per machine) = 1
So, let us say number of new Machines = x
then, x * 8 * 1/72 = 1
x*8 = 72
x = 9
Answer = 9 - 6 = 3
Thanks,
SVD