Machine M can produce x units in 3/4 of the time it takes machine N to produce x units. Machine N can produce x units in 2/3 the time it takes machine O to produce x units. If all three machines are working simultaneously, what fraction of the total output is produced by machine N?
A. 1/2
B. 1/3
C. 4/13
D. 8/29
E. 6/33
The OA is B.
I'm confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Machine M can produce x units in 3/4 of the time it takes...
This topic has expert replies
-
- Moderator
- Posts: 2207
- Joined: Sun Oct 15, 2017 1:50 pm
- Followed by:6 members
-
- Senior | Next Rank: 100 Posts
- Posts: 94
- Joined: Tue Dec 16, 2014 9:50 am
- Location: London, UK
- Thanked: 2 times
- Followed by:4 members
- GMAT Score:770
Let's start with Machine O since this one is the slowest. We can assign it a rate of R.LUANDATO wrote:Machine M can produce x units in 3/4 of the time it takes machine N to produce x units. Machine N can produce x units in 2/3 the time it takes machine O to produce x units. If all three machines are working simultaneously, what fraction of the total output is produced by machine N?
A. 1/2
B. 1/3
C. 4/13
D. 8/29
E. 6/33
The OA is B.
I'm confused by this PS question. Experts, any suggestion about how to solve it? Thanks in advance.
Machine N takes 2/3 of the time of Machine O so it has a rate that is 3/2 faster than Machine O--> rate is 1.5R
Machine M takes 3/4 of the time of Machine N so it has a rate that is 4/3 faster than Machine N --> rate is (4/3)(3/2)R = 2R
Together the machines have a rate of R + 1.5R + 2R = 4.5R
Rate of Machine N/Total Rate = 1.5R/4.5R = 1/3
Answer is B.
GMAT/MBA Expert
- [email protected]
- Elite Legendary Member
- Posts: 10392
- Joined: Sun Jun 23, 2013 6:38 pm
- Location: Palo Alto, CA
- Thanked: 2867 times
- Followed by:511 members
- GMAT Score:800
Hi LUANDATO,
We're told that Machine M can produce X units in 3/4 of the time it takes machine N to produce X units and Machine N can produce X units in 2/3 the time it takes machine O to produce X units. We're asked if all three machines are working simultaneously, what fraction of the total output is produced by machine N. This question can be solved by TESTing VALUES (but you need to focus on the amount of TIME each Machine takes and NOT the value of X).
IF... Machine O takes 12 hours to produce X units and....
Machine N takes (2/3)(12) = 8 hours to produce X units and....
Machine M takes (3/4)(8) = 6 hours to produce X units....
Let's have the Machines work for 24 hours...
Machine O will make (24/12)(X) = 2X units
Machine N will make (24/8)(X) = 3X units
Machine O will make (24/6)(X) = 4X units
2X + 3X + 4X = 9X total units produced. Machine N produces (3X)/(9X) = 1/3 of the units
Final Answer: B
GMAT assassins aren't born, they're made,
Rich
We're told that Machine M can produce X units in 3/4 of the time it takes machine N to produce X units and Machine N can produce X units in 2/3 the time it takes machine O to produce X units. We're asked if all three machines are working simultaneously, what fraction of the total output is produced by machine N. This question can be solved by TESTing VALUES (but you need to focus on the amount of TIME each Machine takes and NOT the value of X).
IF... Machine O takes 12 hours to produce X units and....
Machine N takes (2/3)(12) = 8 hours to produce X units and....
Machine M takes (3/4)(8) = 6 hours to produce X units....
Let's have the Machines work for 24 hours...
Machine O will make (24/12)(X) = 2X units
Machine N will make (24/8)(X) = 3X units
Machine O will make (24/6)(X) = 4X units
2X + 3X + 4X = 9X total units produced. Machine N produces (3X)/(9X) = 1/3 of the units
Final Answer: B
GMAT assassins aren't born, they're made,
Rich
Hi LUANDATO,
Another way to look at the problem can be as follow,
Let the time taken be as
M = 12
N = 8
O = 6
Assume total work be 24 units.
Thus the efficiency of the three machines are asunder,
O = 2
N = 3
M = 4
Total efficiency is 9 (i.e 2 + 3 + 4)units/h
So, work done by N is 3/9 = 1/3. Option B.
Regards!
Another way to look at the problem can be as follow,
Let the time taken be as
M = 12
N = 8
O = 6
Assume total work be 24 units.
Thus the efficiency of the three machines are asunder,
O = 2
N = 3
M = 4
Total efficiency is 9 (i.e 2 + 3 + 4)units/h
So, work done by N is 3/9 = 1/3. Option B.
Regards!
GMAT/MBA Expert
- Jeff@TargetTestPrep
- GMAT Instructor
- Posts: 1462
- Joined: Thu Apr 09, 2015 9:34 am
- Location: New York, NY
- Thanked: 39 times
- Followed by:22 members
Let t = the time it takes machine O to produce x units; then the time it takes machine N to produce x units = (2/3)t, and the time it takes machine M to produce x units = (3/4)(2/3)t = (1/2)t.LUANDATO wrote:Machine M can produce x units in 3/4 of the time it takes machine N to produce x units. Machine N can produce x units in 2/3 the time it takes machine O to produce x units. If all three machines are working simultaneously, what fraction of the total output is produced by machine N?
A. 1/2
B. 1/3
C. 4/13
D. 8/29
E. 6/33
Therefore, the rate of M is x/[(1/2)t] = 2x/t, the rate of N is x/[(2/3)t] = 3x/2t, and the rate of O is x/t. Their combined rate is 2x/t + 3x/2t + x/t = 4x/2t + 3x/2t + 2x/2t = 9x/2t.
If all three machines are working simultaneously, the fraction of the total output that is produced by machine N is:
(3x/2t)/(9x/2t) = 3x/9x = 1/3
Answer: B
Jeffrey Miller
Head of GMAT Instruction
[email protected]
See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews