Running at their respective constant rates, machine X takes 2 days longer to produce w widgets than machines Y. AT these rates, if the two machines together produce 5w/4 widgets in 3 days, how many days would it take machine X alone to produce 2w widgets.
A. 4
B. 6
C. 8
D. 10
E. 12
OA is E
Experts, may you help me here? I am confused. What formulas should I set here?
Running at their respective constant rates, machine X takes
This topic has expert replies
-
- Moderator
- Posts: 772
- Joined: Wed Aug 30, 2017 6:29 pm
- Followed by:6 members
-
- Senior | Next Rank: 100 Posts
- Posts: 94
- Joined: Tue Dec 16, 2014 9:50 am
- Location: London, UK
- Thanked: 2 times
- Followed by:4 members
- GMAT Score:770
Work = Rate * TimeRoland2rule wrote:Running at their respective constant rates, machine X takes 2 days longer to produce w widgets than machines Y. AT these rates, if the two machines together produce 5w/4 widgets in 3 days, how many days would it take machine X alone to produce 2w widgets.
A. 4
B. 6
C. 8
D. 10
E. 12
OA is E
Experts, may you help me here? I am confused. What formulas should I set here?
Machine X:
w = Rx * T
Rx = w/T
Machine Y:
w = Ry * (T-2)
Ry = w/(T-2)
Situation from question:
5w/4 = (Rx + Ry)*3
5w/4 = [w/T + w/(T-2)]*3 --> we can divide through by W
5/4 = [1/T + 1/(T-2)]*3
5/12 = 1/T + 1/(T-2)
5(T)(T-2) = 12(T-2) + 12(T)
5T^2 - 10T = 24T - 24
5T^2 - 34T + 24 = 0
(T-6)(5T-4) = 0
T must be > 2 so the only solution is T = 6
Machine X can produce w widgets in T so it must be able to produce 2w widgets in 2T; given T= 6 then the answer is 2*6 = 12
Answer. E) 12
GMAT/MBA Expert
- Brent@GMATPrepNow
- GMAT Instructor
- Posts: 16207
- Joined: Mon Dec 08, 2008 6:26 pm
- Location: Vancouver, BC
- Thanked: 5254 times
- Followed by:1268 members
- GMAT Score:770
Another approach is to assign a nice value to the job (w)Roland2rule wrote:Running at their respective constant rates, machine X takes 2 days longer to produce w widgets than machines Y. AT these rates, if the two machines together produce 5w/4 widgets in 3 days, how many days would it take machine X alone to produce 2w widgets.
A. 4
B. 6
C. 8
D. 10
E. 12
Let's say that w = 12.
GIVEN: Running at their respective constant rates, machine X takes 2 days longer to produce 12 widgets than machine Y
Let t = time for machine Y to produce 12 widgets
So, t+2 = time for machine X to produce 12 widgets
RATE = output/time
So, machine X's RATE = 12 widgets/(t + 2 days) = 12/(t+2) widgets per day
And machine Y's RATE = 12 widgets/(t days) = 12/t widgets per day
The two machines together produce 5w/4 widgets in 3 days
In other words, The two machines together produce 5(12)/4 widgets in 3 days
Or the two machines together produce 15 widgets in 3 days
This means the COMBINED RATE = 5 widgets per day
So, we can write: 12/(t+2) + 12/t = 5
Multiply both sides by (t+2)(t) to get: 12t + 12t + 24 = 5(t+2)(t)
Simplify: 24t + 24 = 5t² + 10t
Rearrange: 5t² - 14t - 24 = 0
Factor to get: (5t + 6)(t - 4) = 0
So, EITHER t = -6/5 OR t = 4
Since the time cannot be negative, it must be the case that t = 4
If t = 4, then it takes Machine Y 4 days to produce 12 widgets
And it takes Machine X 6 days to produce 12 widgets
How many days would it take machine X alone to produce 2w widgets?
In other words, how many days would it take machine X alone to produce 24 widgets? (since w = 12)
If it takes Machine X 6 days to produce 12 widgets, then it will take Machine X 12 days to produce 24 widgets
Answer: E
Cheers,
Brent
- GMATGuruNY
- GMAT Instructor
- Posts: 15539
- Joined: Tue May 25, 2010 12:04 pm
- Location: New York, NY
- Thanked: 13060 times
- Followed by:1906 members
- GMAT Score:790
Let w = 60 widgets, implying that (5/4)w = (5/4)(60) = 75 widgets.Running at their respective constant rates, machine X takes 2 days longer to produce w widgets than machine Y. At these rates, if the two machines together produce 5w/4 widgets in 3 days, how many days would it take machine X alone to produce 2w widgets?
A) 4
B) 6
C) 8
D) 10
E) 12
Since X and Y together can produce (5/4)w widgets in 3 days, the combined rate for X and Y = w/t = 75/3 = 25 widgets per day.
We can PLUG IN THE ANSWERS, which represent X's time to produce 2w widgets.
When the correct answer choice is plugged in, the combined rate for X and Y will be 25 widgets per day.
D: 10
Here, X can produce 2w widgets in 10 days.
Thus, the time for X to produce w widgets = 5 days.
Since X takes 5 days to produce w=60 widgets, X's rate = w/t = 60/5 = 12 widgets per day.
Since X takes 2 days longer than Y to produce w widgets, Y's time to produce w widgets = 3 days.
Since Y takes 3 days to produce w=60 widgets, Y's rate = w/t = 60/3 = 20 widgets per day.
Combined rate for X and Y = 12+20 = 32 widgets per day.
Here, X and Y are working TOO FAST.
Implication:
X must take LONGER to produce 2w widgets, with the result that X and Y will work more SLOWLY.
The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
GMAT/MBA Expert
- Scott@TargetTestPrep
- GMAT Instructor
- Posts: 7247
- Joined: Sat Apr 25, 2015 10:56 am
- Location: Los Angeles, CA
- Thanked: 43 times
- Followed by:29 members
We can let x = the number of days it takes Machine X to produce w widgets and thus x - 2 = the number of days it takes Machine Y to produce w widgets. Furthermore, the rate of Machine X is w/x and the rate of Machine Y is w/(x - 2). We are given that they can produce 5w/4 widgets in 3 days. Thus, we have:Roland2rule wrote:Running at their respective constant rates, machine X takes 2 days longer to produce w widgets than machines Y. AT these rates, if the two machines together produce 5w/4 widgets in 3 days, how many days would it take machine X alone to produce 2w widgets.
A. 4
B. 6
C. 8
D. 10
E. 12
3(w/x) + 3[w/(x - 2)] = 5w/4
Dividing both sides by w, we have:
3/x + 3/(x - 2) = 5/4
Multiplying both sides by 4x(x - 2), we have:
12(x - 2) + 12x = 5x(x - 2)
12(x - 2) + 12x = 5x(x - 2)
12x - 24 + 12x = 5x^2 - 10x
5x^2 - 34x + 24 = 0
(5x - 4)(x - 6) = 0
x = 4/5 or x = 6
However, x can't be 4/5; if it were, y would be negative. Thus, x must be 6. Since it takes Machine X 6 days to produce w widgets, it will take 12 days to produce 2w widgets.
Answer: E
Scott Woodbury-Stewart