Working at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?

A. 1/2
B. 3/4
C. 1
D. 1 1/4
E. 1 1/2

OA C

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 16207
Joined: Mon Dec 08, 2008 6:26 pm
Location: Vancouver, BC
Thanked: 5254 times
Followed by:1268 members
GMAT Score:770
AAPL wrote:
Tue Jul 05, 2022 1:41 pm
GMAT Prep

Working at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?

A. 1/2
B. 3/4
C. 1
D. 1 1/4
E. 1 1/2

OA C
One approach is to assign a "nice value" to the job.
That is, a value that works well with the given information of 3 hours and 6 hours
So let's say the order consists of making 18 widgets

Working alone at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively
In other words, Machine A can make 18 widgets in 3 hours, which means Machine A's RATE = 6 widgets per hour
This also tells us that Machine B can make 18 widgets in 6 hours, which means Machine B's RATE = 3 widgets per hour

If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?
COMBINED rate = 6 + 3 = 9 widgets per hour

We want to fill 1/2 the order.
1/2 of 18 widgets is 9 widgets
So we want to make 9 widgets

time = output/rate
So, time = 9/9 = 1 hour

Answer: C

Cheers,
Brent
Brent Hanneson - Creator of GMATPrepNow.com
Image

GMAT/MBA Expert

User avatar
GMAT Instructor
Posts: 7222
Joined: Sat Apr 25, 2015 10:56 am
Location: Los Angeles, CA
Thanked: 43 times
Followed by:29 members
AAPL wrote:
Tue Jul 05, 2022 1:41 pm
GMAT Prep

Working at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?

A. 1/2
B. 3/4
C. 1
D. 1 1/4
E. 1 1/2

OA C
We see that rates of machines A and B are 1/3 and 1/6, respectively. Therefore, their combined rate is 1/3 + 1/6 = 1/2, and it will take (1/2) / (1/2) = 1 hour to fill 1/2 of the order.

Answer: C

Scott Woodbury-Stewart
Founder and CEO
[email protected]

Image

See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews

ImageImage