Source: Manhattan Prep
At 8am on Thursday, two workers, A and B, each start working independently to build identical decorative lamps. Worker A completes her lamp at 5pm on Friday, while Worker B completes her lamp sometime during the morning on Friday. If both workers adhere to working hours of 8am to 12pm and 1pm to 5pm each day, at which of the following times might the two workers have completed a single lamp had they worked together at their respective constant rates?
A. Thursday, 1:30pm
B. Thursday, 2:15pm
C. Thursday, 3:00pm
D. Thursday, 4:15pm
E. Friday, 12:00pm
The OA is C
At 8am on Thursday, two workers, A and B, each start working independently to build identical decorative...
This topic has expert replies
-
- Moderator
- Posts: 2209
- Joined: Sun Oct 15, 2017 1:50 pm
- Followed by:6 members
Timer
00:00
Your Answer
A
B
C
D
E
Global Stats
GMAT/MBA Expert
- Scott@TargetTestPrep
- GMAT Instructor
- Posts: 7247
- Joined: Sat Apr 25, 2015 10:56 am
- Location: Los Angeles, CA
- Thanked: 43 times
- Followed by:29 members
Solution:BTGmoderatorLU wrote: ↑Mon Jun 29, 2020 5:04 amSource: Manhattan Prep
At 8am on Thursday, two workers, A and B, each start working independently to build identical decorative lamps. Worker A completes her lamp at 5pm on Friday, while Worker B completes her lamp sometime during the morning on Friday. If both workers adhere to working hours of 8am to 12pm and 1pm to 5pm each day, at which of the following times might the two workers have completed a single lamp had they worked together at their respective constant rates?
A. Thursday, 1:30pm
B. Thursday, 2:15pm
C. Thursday, 3:00pm
D. Thursday, 4:15pm
E. Friday, 12:00pm
The OA is C
We see that a workday is 8 hours (4 hours in the morning and 4 hours in the afternoon). Thus, it takes 2 workdays, or 16 hours, for worker A to complete her lamp, and therefore, her rate is 1/16. We are given that worker B completes her lamp sometime during the morning on Friday. Thus, it takes her more than 1 workday (or 8 hours) and less than 1 ½ workdays (or 12 hours) to complete her lamp, and therefore, her rate is greater than 1/12 but less than 1/8. These two rates are the lower and upper bounds, respectively, of worker B’s rate.
At the upper bound of worker B’s rate, if the two workers work together, it will take 1/(1/16 + 1/8) = 1/(1/16 + 2/16) = 1/(3/16) = 16/3 = 5 ⅓ hr = 5 hr 20 min to complete one single lamp. Therefore, they will finish by 2:20 pm on Thursday (4 hours from 8 am to 12 pm and 1 hr 20 min after 1 pm).
At the lower bound of worker B’s rate, if the two workers work together, it will take 1/(1/16 + 1/12) = 1/(3/48 + 4/48) = 1/(7/48) = 48/7 = 6 6/7 hr ≈ 6 hr 51 min to complete one single lamp. Therefore, they will finish by 3:51 pm on Thursday (4 hours from 8 am to 12 pm and 2 hr 51 min after 1 pm).
Since worker B’s rate is between 1/12 and 1/8, the time when they work together will be between 2:20 pm and 3:51 pm on Thursday. The only time in the given answer choices is choice C: Thursday, 3:00 pm. Thus choice C is the correct answer.
Answer: C
Scott Woodbury-Stewart
Founder and CEO
[email protected]
See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews