Each of 10 machines work at the same constant rate doing a certain job.The amount of time needed by he 10 machines , working together , to complete the job is 16 hrs.How many hours would be needed if only 8 of the machines, working together , were used to complete the job
18
20
22
24
26
time & work problm from Grep - hw do i solve this
This topic has expert replies
-
- Senior | Next Rank: 100 Posts
- Posts: 66
- Joined: Wed Feb 20, 2008 6:23 pm
- Thanked: 2 times
-
- Senior | Next Rank: 100 Posts
- Posts: 62
- Joined: Fri Dec 21, 2007 2:58 pm
- Location: Fremont , California
- Thanked: 3 times
Each of 10 machines work at the same constant rate doing a certain job.The amount of time needed by he 10 machines , working together , to complete the job is 16 hrs.How many hours would be needed if only 8 of the machines, working together , were used to complete the job
Answer: 20
More machines less number of hours to complete the Job.
So, Number of Machines and Hours are Inversely proportional
M1 * H1 = M2 * H2
10 * 16 = 8 * H2
=> 8 * H2 = 10 * 16
=> H2 = 10 * 2 = 20
Answer: 20
More machines less number of hours to complete the Job.
So, Number of Machines and Hours are Inversely proportional
M1 * H1 = M2 * H2
10 * 16 = 8 * H2
=> 8 * H2 = 10 * 16
=> H2 = 10 * 2 = 20
- AleksandrM
- Legendary Member
- Posts: 566
- Joined: Fri Jan 04, 2008 11:01 am
- Location: Philadelphia
- Thanked: 31 times
- GMAT Score:640
kishore,
Can you elaborate a little bit. You approach is not completely clear to me. Thanks.
Can you elaborate a little bit. You approach is not completely clear to me. Thanks.
Each machine performs equally so, no of machine is inversaly proportional to the time take by those machines to finish the work
means m = k/h wheren m = no of machines and h = no of hours and k = constant
when m = 10, h = 16 so 10 = k/16 => k = 160
when m = 8, h = k/m = 160/8 = 20
means m = k/h wheren m = no of machines and h = no of hours and k = constant
when m = 10, h = 16 so 10 = k/16 => k = 160
when m = 8, h = k/m = 160/8 = 20
-
- Senior | Next Rank: 100 Posts
- Posts: 52
- Joined: Mon Jan 14, 2008 7:46 pm
- Thanked: 3 times
Hi All,
The explaination given by all of you makes sense. I was trying to solve this question by a method learned from Princeton Review but it doesn't seem to work.
10 Machines / 16 hours = 8 Machines/x hours
The answer would be 12.8 but it is clearly wrong.
Could someone please explain me, why this approach is not working for this question ?
The explaination given by all of you makes sense. I was trying to solve this question by a method learned from Princeton Review but it doesn't seem to work.
10 Machines / 16 hours = 8 Machines/x hours
The answer would be 12.8 but it is clearly wrong.
Could someone please explain me, why this approach is not working for this question ?
Never GiveUp For Any Reason
GMAT/MBA Expert
- Ian Stewart
- GMAT Instructor
- Posts: 2621
- Joined: Mon Jun 02, 2008 3:17 am
- Location: Montreal
- Thanked: 1090 times
- Followed by:355 members
- GMAT Score:780
That ought to be:gmataspirant wrote:Hi All,
The explaination given by all of you makes sense. I was trying to solve this question by a method learned from Princeton Review but it doesn't seem to work.
10 Machines / 16 hours = 8 Machines/x hours
The answer would be 12.8 but it is clearly wrong.
Could someone please explain me, why this approach is not working for this question ?
10 machines times 16 hours = 8 machines times x hours
This question is similar to other questions that use the (archaic) phrase 'man hours'. I'll use the term 'person hours' instead. If 20 people work together for 30 hours to complete a job, the job requires 20*30 = 600 'person hours' to complete. So if 15 people work on the job instead, they'll need to work together for 40 hours, since 15*40 = 600.
In this question, 10 machines working for 16 hours do 160 hours of machine work. 8 machines would need to do 20 hours each.
-
- Senior | Next Rank: 100 Posts
- Posts: 52
- Joined: Mon Jan 14, 2008 7:46 pm
- Thanked: 3 times
Thanks Ian,
I just worked the problem. It is no different than what already been said.
Formula:
Amount of Work = Rate X Time
10 Machines Scenario::
As amount of work is not given, let’s assume that Amount of work to be “k”.
k = 10 * 6 = 160
8 Machine Scenario::
From the previous calculation we know the amount of work to be done is 160
160 = 8x
x=20
I just worked the problem. It is no different than what already been said.
Formula:
Amount of Work = Rate X Time
10 Machines Scenario::
As amount of work is not given, let’s assume that Amount of work to be “k”.
k = 10 * 6 = 160
8 Machine Scenario::
From the previous calculation we know the amount of work to be done is 160
160 = 8x
x=20
Never GiveUp For Any Reason