Working alone, three persons P, Q, and R can do a certain job in 10, 12, and 15 hours respectively. What is the ratio of the maximum and minimum time taken to complete the job, if at every hour, at least 1 person must work?
A. 1:3
B. 1:2
C. 1:1
D. 3:1
E. 15:4
OA E
Source: e-GMAT
Working alone, three persons P, Q, and R can do a certain
This topic has expert replies
-
- Moderator
- Posts: 7187
- Joined: Thu Sep 07, 2017 4:43 pm
- Followed by:23 members
Timer
00:00
Your Answer
A
B
C
D
E
Global Stats
GMAT/MBA Expert
- Jay@ManhattanReview
- GMAT Instructor
- Posts: 3008
- Joined: Mon Aug 22, 2016 6:19 am
- Location: Grand Central / New York
- Thanked: 470 times
- Followed by:34 members
Nice questionBTGmoderatorDC wrote:Working alone, three persons P, Q, and R can do a certain job in 10, 12, and 15 hours respectively. What is the ratio of the maximum and minimum time taken to complete the job, if at every hour, at least 1 person must work?
A. 1:3
B. 1:2
C. 1:1
D. 3:1
E. 15:4
OA E
Source: e-GMAT
The work will be completed in maximum time if only one among P, Q and R work; since R is the slowest, it is R who would complete the work in maximum time -- 15 hours.
Now the computation of minimum time is tricky.
The phrase, "at least 1 person must work" means that one, two, or even three persons can work together.
It is obvious that the work will be completed in minimum time if all three work together.
Time taken by P, Q and R, working together = Reciprocal of (1/10 + 1/12 + 1/15) = 180/45 hours
The ratio of the maximum and minimum time taken to complete the job = 15 / (180/45) = 15/4.
The correct answer: E
Hope this helps!
-Jay
_________________
Manhattan Review GMAT Prep
Locations: Manhattan Review India | Manhattan Review Hyderabad | Begumpet GMAT Courses | Madhapur GRE Prep | and many more...
Schedule your free consultation with an experienced GMAT Prep Advisor! Click here.
- GMATGuruNY
- GMAT Instructor
- Posts: 15539
- Joined: Tue May 25, 2010 12:04 pm
- Location: New York, NY
- Thanked: 13060 times
- Followed by:1906 members
- GMAT Score:790
Let the job = the LCM of the 3 times = 60 widgets.BTGmoderatorDC wrote:Working alone, three persons P, Q, and R can do a certain job in 10, 12, and 15 hours respectively. What is the ratio of the maximum and minimum time taken to complete the job, if at every hour, at least 1 person must work?
A. 1:3
B. 1:2
C. 1:1
D. 3:1
E. 15:4
Maximum time:
The maximum time is yielded when the slowest person -- R -- works alone.
Since R takes 15 hours to complete the 60-widget job, the maximum time = 15 hours.
Minimum time:
The minimum time is yielded when all 3 people work together.
Since P takes 10 hours to complete the 60-widget job, P's rate = 60/10 = 6 widgets per hour.
since Q takes 12 hours to complete the 60-widget job, Q's rate = 60/12 = 5 widgets per hour.
Since R takes 15 hours to complete the 60-widget job, R's rate = 60/15 = 4 widgets per hour.
Since the combined rate for P+Q+R = 6+5+4 = 15 widgets per hour, the time for P+Q+R to complete the 60-widget job = 60/15 = 4 hours.
Resulting ratio:
(max time) : (min time) = 15:4.
The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
GMAT/MBA Expert
- Scott@TargetTestPrep
- GMAT Instructor
- Posts: 7222
- Joined: Sat Apr 25, 2015 10:56 am
- Location: Los Angeles, CA
- Thanked: 43 times
- Followed by:29 members
The maximum amount of time to complete the job is if R , the slowest worker, works alone, and it will take him 15 hours to complete it.BTGmoderatorDC wrote:Working alone, three persons P, Q, and R can do a certain job in 10, 12, and 15 hours respectively. What is the ratio of the maximum and minimum time taken to complete the job, if at every hour, at least 1 person must work?
A. 1:3
B. 1:2
C. 1:1
D. 3:1
E. 15:4
The minimum amount of time to complete the job is if all three people work together, and it will take them 1/(1/10 + 1/12 + 1/15) = 1/(6/60 + 5/60 + 4/60) = 1/(15/60) = 60/15 = 4 hours to complete it.
Therefore, the ratio is 15:4.
Answer: E