A work crew of 4 Men takes 5 days to complete one-half

This topic has expert replies
Moderator
Posts: 2246
Joined: Sun Oct 29, 2017 2:08 pm
Followed by:2 members
A work crew of 4 Men takes 5 days to complete one-half of a job. If 6 men are then added to the crew and the men continue to work at the same rate, how many days will it take the enlarged crew to do the rest of the job?

A. 2
B. 3
C. 3 1/3
D. 4
E. 4 4/5

The OA is A.

Suppose 1 man can do the work in X days.

So 4 men will do in,

4/X = 1/5*1/2 as half job is done

X=40

Now 6 more are added then

10/40=1/2*1/d for remaining half job

d=2 Number of days. Option A.

Has anyone another approach to solve this PS question? Thanks in advance.

User avatar
GMAT Instructor
Posts: 15539
Joined: Tue May 25, 2010 12:04 pm
Location: New York, NY
Thanked: 13060 times
Followed by:1906 members
GMAT Score:790

by GMATGuruNY » Thu Apr 05, 2018 1:28 pm
AAPL wrote:A work crew of 4 Men takes 5 days to complete one-half of a job. If 6 men are then added to the crew and the men continue to work at the same rate, how many days will it take the enlarged crew to do the rest of the job?

A. 2
B. 3
C. 3 1/3
D. 4
E. 4 4/5
Let the rate for each man = 1 unit per day, implying that the combined rate for 4 men = 4 units per day.
Since the rate for the original 4-men crew = 4 units per day, the amount of work produced in the first 5 days = rt = 4*5 = 20 units.
Since these 20 units constitute 1/2 the job -- implying that the whole job is 40 units -- the remaining work = 20 units.
When 6 men are added -- increasing the total number of men to 10 -- the rate increases to 10 units for day.
Since the rate for the 10-men crew = 10 units per day, the time for the 10-men crew to produce the remaining 20 units = w/r = 20/10 = 2 days.

The correct answer is A.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.

As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.

For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3

GMAT/MBA Expert

Junior | Next Rank: 30 Posts
Posts: 23
Joined: Mon Mar 12, 2018 9:53 am

TTT

by Jake@ThePrincetonReview » Thu Apr 05, 2018 3:51 pm
Another way to think about this kind of problem (without doing algebra) is to plug in a number of "widgets" to represent the entire job. Since we're working with 4, 5, and 6, let's make the job equal to 120 widgets (a nice multiple of 4, 5, and 6).
Job = 120 Widgets.

Now, you're told that it takes 4 men 5 days to complete half the job, so that's 20 man-days to complete 60 widgets, which would break down to 1 man = 3 widgets/day.

Next, you're asked to calculate how many days it would take to complete the job if we add 6 men.
Completing the job = 60 more widgets
And now we have 10 men, who we know can each complete 3 widgets per day. So that's 30 widgets per day completed by 10 men, and therefore, the 10 men would be able to complete the remaining 60 widgets in 2 days.

Jake Schiff
GMAT Instructor and MasterTrainer


Image
Jake Schiff
GMAT Instructor and Master Trainer
Image
Curious How You'll Score? Take a FREE GMAT® practice test or sample class
Ready to Prep? Exclusive discounts for Beat The GMAT® members HERE