It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each
technician working at the same rate. If 6 technicians start to build the server at 11:00 a.m., and one technician
per hour is added beginning at 5:00 p.m., at what time will the server be complete?
A. 6:40 p.m.
B. 7:00 p.m.
C. 7:20 p.m.
D. 7:40 p.m.
E. 8:00 p.m.
OA E
I am completely lost with this question.
Please provide some thorough answer with detailed explanation. Thanks alot in advance.
Work - Rate Problem - Computer Server
This topic has expert replies
GMAT/MBA Expert
- Anurag@Gurome
- GMAT Instructor
- Posts: 3835
- Joined: Fri Apr 02, 2010 10:00 pm
- Location: Milpitas, CA
- Thanked: 1854 times
- Followed by:523 members
- GMAT Score:770
Solution:
It takes 6 technicians a total of 10 hours to build a server.
So, in 1 hour, 6 technicians do (1/10)th part of the work.
Also, it takes 1 technician a total of 60 hours to build the server.
Or, in 1 hour, 1 technician does 1/60th part of the work
So from, 11 a.m to 5 p.m which is 6 hours, 6 technicians do (1/10)*6 = (3/5)th part of the work.
Or (2/5)th part of the work is left.
Now after 5 pm, there are 7 technicians who work for 1 hour till 6 pm.
So, they complete (7/60)th part of the work.
Or 2/5 - 7/60 = (17/60)th part of the work is left.
Now 8 technicians work from 6 pm to 7 pm for 1hour.
So, they do (8/60) th part of the work.
Remaining work to be done is (17/60 - 8/60) = 9/60.
Now 9 technicians work from 7 pm to 8 pm for 1 hour.
Now 9 technicians do (9/60)th part of the work upto 8 pm.
Since (9/60) th of the work was left to be done, these 9 technicians complete the work by 8 pm.
The correct answer is (E).
It takes 6 technicians a total of 10 hours to build a server.
So, in 1 hour, 6 technicians do (1/10)th part of the work.
Also, it takes 1 technician a total of 60 hours to build the server.
Or, in 1 hour, 1 technician does 1/60th part of the work
So from, 11 a.m to 5 p.m which is 6 hours, 6 technicians do (1/10)*6 = (3/5)th part of the work.
Or (2/5)th part of the work is left.
Now after 5 pm, there are 7 technicians who work for 1 hour till 6 pm.
So, they complete (7/60)th part of the work.
Or 2/5 - 7/60 = (17/60)th part of the work is left.
Now 8 technicians work from 6 pm to 7 pm for 1hour.
So, they do (8/60) th part of the work.
Remaining work to be done is (17/60 - 8/60) = 9/60.
Now 9 technicians work from 7 pm to 8 pm for 1 hour.
Now 9 technicians do (9/60)th part of the work upto 8 pm.
Since (9/60) th of the work was left to be done, these 9 technicians complete the work by 8 pm.
The correct answer is (E).
Anurag Mairal, Ph.D., MBA
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)
Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/
GMAT Expert, Admissions and Career Guidance
Gurome, Inc.
1-800-566-4043 (USA)
Join Our Facebook Groups
GMAT with Gurome
https://www.facebook.com/groups/272466352793633/
Admissions with Gurome
https://www.facebook.com/groups/461459690536574/
Career Advising with Gurome
https://www.facebook.com/groups/360435787349781/
- Rich@VeritasPrep
- GMAT Instructor
- Posts: 147
- Joined: Tue Aug 25, 2009 7:57 pm
- Location: New York City
- Thanked: 76 times
- Followed by:17 members
- GMAT Score:770
The 6 technicians would take 10 hours to complete the job. They work from 11 to 5, which is a 6 hour period. That means that if the 6 technicians continued with the rest of the job, it would take 10-6 = 4 hours.
Since 6 technicians would complete the remaining work in 4 hours, that means 1 technician would complete the work in 24 hours. (You can see this from the work rate formula W = r*t = (6*tech rate)*4 = 24 * tech rate)
This also means 1 technician would complete 1/24 of the remaining work in one hour.
We add a seventh technician at 5pm, and the seven work for an hour. That means they get 7/24 of the remaining work done.
We add an eighth technician at 6pm, and the eight work for an hour. That means they get another 8/24 done (of the work left at 5pm).
We add a ninth technician at 7pm, and the nine work for an hour. That means they get another 9/24 (of the work left at 5pm) done at 8pm.
7/24+8/24+9/24 = 24/24 = 1 = complete job.
Answer: E
Since 6 technicians would complete the remaining work in 4 hours, that means 1 technician would complete the work in 24 hours. (You can see this from the work rate formula W = r*t = (6*tech rate)*4 = 24 * tech rate)
This also means 1 technician would complete 1/24 of the remaining work in one hour.
We add a seventh technician at 5pm, and the seven work for an hour. That means they get 7/24 of the remaining work done.
We add an eighth technician at 6pm, and the eight work for an hour. That means they get another 8/24 done (of the work left at 5pm).
We add a ninth technician at 7pm, and the nine work for an hour. That means they get another 9/24 (of the work left at 5pm) done at 8pm.
7/24+8/24+9/24 = 24/24 = 1 = complete job.
Answer: E
Rich Zwelling
GMAT Instructor, Veritas Prep
GMAT Instructor, Veritas Prep
- manpsingh87
- Master | Next Rank: 500 Posts
- Posts: 436
- Joined: Tue Feb 08, 2011 3:07 am
- Thanked: 72 times
- Followed by:6 members
let work to be 60 units,sal_xcool wrote:It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each
technician working at the same rate. If 6 technicians start to build the server at 11:00 a.m., and one technician
per hour is added beginning at 5:00 p.m., at what time will the server be complete?
A. 6:40 p.m.
B. 7:00 p.m.
C. 7:20 p.m.
D. 7:40 p.m.
E. 8:00 p.m.
OA E
I am completely lost with this question.
Please provide some thorough answer with detailed explanation. Thanks alot in advance.
so from 11 to 5pm 6 technicians worked for 6 hours thus they have done 6*6 = 36 units of work. Therefore, remaining left over work is 24 units.
now at 6 pm work would be 7 as new person has joined in, similarly at 7 pm work would be 8, and at 8 work would be 9
adding these work unit we get 7+8+9 = 24.
hence the work will be completed by 8 pm.!!!
O Excellence... my search for you is on... you can be far.. but not beyond my reach!
- sanju09
- GMAT Instructor
- Posts: 3650
- Joined: Wed Jan 21, 2009 4:27 am
- Location: India
- Thanked: 267 times
- Followed by:80 members
- GMAT Score:760
sal_xcool wrote:It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each
technician working at the same rate. If 6 technicians start to build the server at 11:00 a.m., and one technician
per hour is added beginning at 5:00 p.m., at what time will the server be complete?
A. 6:40 p.m.
B. 7:00 p.m.
C. 7:20 p.m.
D. 7:40 p.m.
E. 8:00 p.m.
OA E
I am completely lost with this question.
Please provide some thorough answer with detailed explanation. Thanks alot in advance.
If it takes 6 technicians a total of 10 hours to complete the said task with each technician working at the same rate, then the work rate per technician is 1/60 per hour.
From 11:00 a.m. to 5:00 p.m. the same day, there is 6 hours time, during which the unit of 6 technicians would have fixed 6/10 or 3/5 or 36/60 of the new server from Direct Computer, with only 24/60 of the work remaining. We'll have to be watchful as at what hour the sum of all numerators in the following story becomes or exceeds 24 to make certain that the task is now over.
Now, 7 technicians in another hour (i.e. by 6:00 p.m.) would fix 7/60 of the whole task, and then 8 technicians in another hour (i.e. by 7:00 p.m.) would fix 8/60 of the whole task, and then 9 technicians in another hour (i.e. by 8:00 p.m.) would fix 9/60 of the whole task...STOP, since 7 + 8 + 9 = 24, and that happened at [spoiler]8:00 pm
E[/spoiler]
The mind is everything. What you think you become. -Lord Buddha
Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001
www.manyagroup.com
Sanjeev K Saxena
Quantitative Instructor
The Princeton Review - Manya Abroad
Lucknow-226001
www.manyagroup.com
- GMATGuruNY
- GMAT Instructor
- Posts: 15539
- Joined: Tue May 25, 2010 12:04 pm
- Location: New York, NY
- Thanked: 13060 times
- Followed by:1906 members
- GMAT Score:790
When the job is undefined, plug in. Plugging in will achieve the same result as other approaches and save us from having to deal with messy fractions.sal_xcool wrote:It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each
technician working at the same rate. If 6 technicians start to build the server at 11:00 a.m., and one technician
per hour is added beginning at 5:00 p.m., at what time will the server be complete?
A. 6:40 p.m.
B. 7:00 p.m.
C. 7:20 p.m.
D. 7:40 p.m.
E. 8:00 p.m.
OA E
I am completely lost with this question.
Please provide some thorough answer with detailed explanation. Thanks alot in advance.
Let rate per worker = 1 unit/hour.
Every hour 6 workers produce 6*1 = 6 units.
Over 10 hours, 10*6 = 60 units are produced. This is the value of the job.
From 11am-5pm, 6 workers will produce r*t = 6*6 = 36 units.
Work remaining = 60-36 = 24 units.
Each hour thereafter another worker is added. During the next hour 7 units will be produced, then 8, then 9.
7+8+9 = 24 units.
In 3 hours, the job will have been completed.
5pm + 3 hours = 8pm.
The correct answer is E.
Private tutor exclusively for the GMAT and GRE, with over 20 years of experience.
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
Followed here and elsewhere by over 1900 test-takers.
I have worked with students based in the US, Australia, Taiwan, China, Tajikistan, Kuwait, Saudi Arabia -- a long list of countries.
My students have been admitted to HBS, CBS, Tuck, Yale, Stern, Fuqua -- a long list of top programs.
As a tutor, I don't simply teach you how I would approach problems.
I unlock the best way for YOU to solve problems.
For more information, please email me (Mitch Hunt) at [email protected].
Student Review #1
Student Review #2
Student Review #3
GMAT/MBA Expert
- Scott@TargetTestPrep
- GMAT Instructor
- Posts: 7247
- Joined: Sat Apr 25, 2015 10:56 am
- Location: Los Angeles, CA
- Thanked: 43 times
- Followed by:29 members
sal_xcool wrote:It takes 6 technicians a total of 10 hours to build and program a new server from Direct Computer, with each technician working at the same rate. If 6 technicians start to build the server at 11:00 a.m., and one technician per hour is added beginning at 5:00 p.m., at what time will the server be complete?
A. 6:40 p.m.
B. 7:00 p.m.
C. 7:20 p.m.
D. 7:40 p.m.
E. 8:00 p.m.
We are given that 6 technicians can complete a job in 10 hours. Since rate = work/time, the rate of the 6 technicians is 1/10. Thus, the rate of 1 technician is (1/10)/6 = 1/60.
We see that 6 technicians work from 11:00 AM to 5:00 PM, or 6 hours. Since rate x time = work, those technicians complete 1/10 x 6 = 6/10 = 3/5 of the job.
If another technician is added to the job at 5:00 PM, the new rate for the technicians is (1/60) x 7 = 7/60, and thus all 7 technicians complete 7/60 of the job in the hour from 5:00 PM to 6:00 PM.
Thus, 3/5 + 7/60 = 36/60 + 7/60 = 43/60 of the job will be completed.
If another technician is added to the job at 6:00 PM, the new rate for the technicians is (1/60) x 8 = 8/60, and thus all 8 technicians complete 8/60 of the job in the hour from 6:00 PM to 7:00 PM.
Thus, 43/60 + 8/60 = 51/60 of the job will be completed.
If another technician is added to the job at 7:00 PM, the new rate for the technicians is (1/60) x 9 = 9/60, and thus all 9 technicians complete 9/60 of the job in the hour from 7:00 PM to 8:00 PM.
Thus, 51/60 + 9/60 = 60/60 = 1 whole job will be completed at 8:00 PM.
Answer: E
Scott Woodbury-Stewart
Founder and CEO
[email protected]
See why Target Test Prep is rated 5 out of 5 stars on BEAT the GMAT. Read our reviews