136 work and time

This topic has expert replies
Master | Next Rank: 500 Posts
Posts: 226
Joined: Sun Aug 09, 2009 4:34 am

136 work and time

by ern5231 » Tue Oct 06, 2009 3:26 pm
Two machines A and B. In one hour A makes 1000 products, B makes 700 products. Together they must take complete 12000 products in 8 hours. Suppose, B works 6.4 hours(with A then only A works). Then minimum how many hours does A work to finish the job?

I got the answer as 7.7. Just want to confirm. I don't have an OA for this

Legendary Member
Posts: 727
Joined: Sun Jun 08, 2008 9:32 pm
Thanked: 8 times
Followed by:1 members

Re: 136 work and time

by umaa » Tue Oct 06, 2009 6:53 pm
ern5231 wrote:Two machines A and B. In one hour A makes 1000 products, B makes 700 products. Together they must take complete 12000 products in 8 hours. Suppose, B works 6.4 hours(with A then only A works). Then minimum how many hours does A work to finish the job?

I got the answer as 7.7. Just want to confirm. I don't have an OA for this
I got 1 hours 7 mins. Where did you get the question?
What we think, we become

Master | Next Rank: 500 Posts
Posts: 226
Joined: Sun Aug 09, 2009 4:34 am

by ern5231 » Tue Oct 06, 2009 10:37 pm
got this one from freshersworld.com

Master | Next Rank: 500 Posts
Posts: 182
Joined: Sun Aug 02, 2009 7:19 pm
Thanked: 18 times
GMAT Score:680

by sanjana » Wed Oct 07, 2009 1:28 am
1hr 7 min is the correct answer.

Explanation :

A
Rate : 1000 prod/hr
B
Rate : 700 prod/hr

Combined rate : 1700 prod/hr

They work together for 6.4 Hrs
Therefore,number of products produced in 6.4 hrs is
1700*6.4 = 10880 prod

Now A has to work alone to produce 12000-10880 = 1120 prods

Therefore
Rate : 1000 prod/hr
Work : 1120 prod
Hence,time = 1120/1000 = 1.12 Hrs = 67min = 1hr 7 min.