Ok here is how I attempted this problem, want to know if my logic is correct
R's rate: 1/36
S's rate: 1/18
1/36x + 1/18x = 1/2
x = 6
I think I just got lucky with this one...
Do you have to go one step furthur to say 36 hours / 6 = 6 ???
Not sure...
GMAT Prep - Rates
This topic has expert replies
-
- GMAT Instructor
- Posts: 26
- Joined: Sun Jul 06, 2008 8:53 am
- Location: New York City
- Thanked: 1 times
Hi,
This question is not so bad if you convert the rates into whole numbers and then just test the answer choices.
We are not told how big the job is, so you can make up a job that is a multiple of the two rates (18 and 36). So the job can be 36 units.
Since R can complete the job in 36 hours, R's rate is 1 unit/hour. Likewise, since S can complete the job in 18 hours, S's rate is 2 units/hour.
If the entire job was completed in only 2 hours, as the question tells us, the combined rate for the entire job of 36 units was 18 units per hour. Thus, we want to find out how many S and R machines working together can work at a combined rate of 18 units per hour, where S and R each has the same number of machines running.
Here, you can just test the answer choices. If you are testing the answer choices, it is best to start with (C), because if (C) is wrong you can tell whether you need a bigger or smaller number.
(C) = 6. If 6 R machines were working at a rate of 1 unit per hour, they would produce units at a combined rate of 6 units per hour. If 6 S machines worked at a rate of 2 units per hour, they would produce units at a combined rate of 12 units per hours. Thus, the combined rate of 6 R machines and 6 S machine working together is, indeed, 18 units per hour -- which is what we are looking for.
Cheers,
This question is not so bad if you convert the rates into whole numbers and then just test the answer choices.
We are not told how big the job is, so you can make up a job that is a multiple of the two rates (18 and 36). So the job can be 36 units.
Since R can complete the job in 36 hours, R's rate is 1 unit/hour. Likewise, since S can complete the job in 18 hours, S's rate is 2 units/hour.
If the entire job was completed in only 2 hours, as the question tells us, the combined rate for the entire job of 36 units was 18 units per hour. Thus, we want to find out how many S and R machines working together can work at a combined rate of 18 units per hour, where S and R each has the same number of machines running.
Here, you can just test the answer choices. If you are testing the answer choices, it is best to start with (C), because if (C) is wrong you can tell whether you need a bigger or smaller number.
(C) = 6. If 6 R machines were working at a rate of 1 unit per hour, they would produce units at a combined rate of 6 units per hour. If 6 S machines worked at a rate of 2 units per hour, they would produce units at a combined rate of 12 units per hours. Thus, the combined rate of 6 R machines and 6 S machine working together is, indeed, 18 units per hour -- which is what we are looking for.
Cheers,
David Stoll
The Princeton Review
The Princeton Review
-
- Newbie | Next Rank: 10 Posts
- Posts: 7
- Joined: Wed Apr 23, 2008 12:10 am
- Location: Chennai
Machine A takes 36 hours
Machine B takes 18 hours.
Let the work is 72 units.
So rate of A is 2 unit/hour
rate of B = 4 unit/hour
combined rate = 6 unit/hour
so, to finish the work, they need 12 hours(72/6).
to finish the work in two hours, they need to do 36 unit/hour
So, amount of unit they need is 6*6.
so they need 6 of each type.
Machine B takes 18 hours.
Let the work is 72 units.
So rate of A is 2 unit/hour
rate of B = 4 unit/hour
combined rate = 6 unit/hour
so, to finish the work, they need 12 hours(72/6).
to finish the work in two hours, they need to do 36 unit/hour
So, amount of unit they need is 6*6.
so they need 6 of each type.
Life is Adventure.
I solved this problem the exact same way. The reason I used x to multiply the rates of each machine is because the question stem said the same number of each type of machine was used.. However my way of solving was very different from Shrindidhi because I put the x on the bottom.rosh26 wrote:Ok here is how I attempted this problem, want to know if my logic is correct
R's rate: 1/36
S's rate: 1/18
1/36x + 1/18x = 1/2
x = 6
I think I just got lucky with this one...
Do you have to go one step furthur to say 36 hours / 6 = 6 ???
Not sure...
Which is the correct method for setting up the equation. and Why?
x/36 + x/16 = 1/2
or
1/36x + 1/18x = 1/2
-
- Master | Next Rank: 500 Posts
- Posts: 431
- Joined: Sat Jan 10, 2009 9:32 am
- Thanked: 16 times
- Followed by:1 members
The FIRST method that you have laid out is absolutely not correct.anniev2 wrote:I solved this problem the exact same way. The reason I used x to multiply the rates of each machine is because the question stem said the same number of each type of machine was used.. However my way of solving was very different from Shrindidhi because I put the x on the bottom.rosh26 wrote:Ok here is how I attempted this problem, want to know if my logic is correct
R's rate: 1/36
S's rate: 1/18
1/36x + 1/18x = 1/2
x = 6
I think I just got lucky with this one...
Do you have to go one step furthur to say 36 hours / 6 = 6 ???
Not sure...
Which is the correct method for setting up the equation. and Why?
x/36 + x/16 = 1/2
or
1/36x + 1/18x = 1/2
R: rate at which 1 m/c works= 1/36
rate at which n m/c will work= n/36 (not 1/36n)
S: rate at which 1 m/c works= 1/18
rate at which n m/c will work= n/18
Combined rates completes the work in 2 hrs.
rate at which R+S works = 1/2
n/36 + n/18 = 1/2 and solve. Hope it's clear.
Last edited by kanha81 on Thu Apr 30, 2009 11:49 am, edited 1 time in total.
Want to Beat GMAT.
Always do what you're afraid to do. Whoooop GMAT
Always do what you're afraid to do. Whoooop GMAT