GMAT Prep
Working at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?
A. 1/2
B. 3/4
C. 1
D. 1 1/4
E. 1 1/2
OA C
Solve 700-Level Algebra Qs In 90 Secs!
Master 700-level Inequalities and Absolute Value Questions
Attend this free GMAT Algebra Webinar and learn how to master the most challenging Inequalities and Absolute Value problems with ease.
Working alone at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6
This topic has expert replies
GMAT/MBA Expert
- [email protected]
- GMAT Instructor
- Posts: 16201
- Joined: Mon Dec 08, 2008 6:26 pm
- Location: Vancouver, BC
- Thanked: 5254 times
- Followed by:1268 members
- GMAT Score:770
One approach is to assign a "nice value" to the job.AAPL wrote: ↑Tue Jul 05, 2022 1:41 pmGMAT Prep
Working at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?
A. 1/2
B. 3/4
C. 1
D. 1 1/4
E. 1 1/2
OA C
That is, a value that works well with the given information of 3 hours and 6 hours
So let's say the order consists of making 18 widgets
Working alone at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively
In other words, Machine A can make 18 widgets in 3 hours, which means Machine A's RATE = 6 widgets per hour
This also tells us that Machine B can make 18 widgets in 6 hours, which means Machine B's RATE = 3 widgets per hour
If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?
COMBINED rate = 6 + 3 = 9 widgets per hour
We want to fill 1/2 the order.
1/2 of 18 widgets is 9 widgets
So we want to make 9 widgets
time = output/rate
So, time = 9/9 = 1 hour
Answer: C
Cheers,
Brent
GMAT/MBA Expert
- [email protected]
- GMAT Instructor
- Posts: 6896
- Joined: Sat Apr 25, 2015 10:56 am
- Location: Los Angeles, CA
- Thanked: 43 times
- Followed by:29 members
We see that rates of machines A and B are 1/3 and 1/6, respectively. Therefore, their combined rate is 1/3 + 1/6 = 1/2, and it will take (1/2) / (1/2) = 1 hour to fill 1/2 of the order.AAPL wrote: ↑Tue Jul 05, 2022 1:41 pmGMAT Prep
Working at their respective constant rates, machine A and machine B can fill a certain order in 3 hours and 6 hours, respectively. If the two machines work simultaneously at their respective constant rates, how many hours does it take the two machines to fill 1/2 of that order?
A. 1/2
B. 3/4
C. 1
D. 1 1/4
E. 1 1/2
OA C
Answer: C