Akhil must complete a project that is divided into seven subtasks by midnight on Sunday. He can only complete one

This topic has expert replies
Moderator
Posts: 7187
Joined: Thu Sep 07, 2017 4:43 pm
Followed by:23 members

Timer

00:00

Your Answer

A

B

C

D

E

Global Stats

Untitled.png
Akhil must complete a project that is divided into seven subtasks by midnight on Sunday. He can only complete one subtask each day, starting Monday morning, though the subtasks can be completed in any order. The table shows each subtask as a fraction of the total work for the project. If he must complete more than half of the work for the project before Friday, is subtask S completed before Friday?

(1) Subtask R is completed on Friday and Subtask V is completed on Saturday.

(2) Subtask P is completed on Thursday and Subtask Q is completed on Monday.



OA A

Source: Manhattan Prep