Akhil must complete a project that is divided into seven subtasks by midnight on Sunday. He can only complete one subtas
This topic has expert replies
Timer
00:00
Your Answer
A
B
C
D
E
Global Stats
(1) Subtask \(R\) is completed on Friday and Subtask \(V\) is completed on Saturday.
(2) Subtask \(P\) is completed on Thursday and Subtask \(Q\) is completed on Monday.
Answer: A
Source: Manhattan GMAT