In NutsAndBolts factory, one machine produces only nuts at the rate of 100 nuts per minute and needs to be cleaned for 5 minutes after production of every 1000 nuts. Another machine produces only bolts at the rate of 75 bolts per minute and needs to be cleaned for 10 minutes after production of every 1500 bolts. If both the machines start production at the same time, what is the minimum duration required for producing 9000 pairs of nuts and bolts?
130 minutes
135 minutes
170 minutes
180 minutes
200 minutes
130 minutes
135 minutes
170 minutes
180 minutes
200 minutes
My Websites:
www.mba.webmaggu.com - India's social Network for MBA Aspirants
www.deal.webmaggu.com -India's online discount, coupon, free stuff informer.
www.dictionary.webmaggu.com - A compact free online dictionary with images.
Nothing is Impossible, even Impossible says I'm possible.
www.mba.webmaggu.com - India's social Network for MBA Aspirants
www.deal.webmaggu.com -India's online discount, coupon, free stuff informer.
www.dictionary.webmaggu.com - A compact free online dictionary with images.
Nothing is Impossible, even Impossible says I'm possible.