20 workmen can make 35 widgets in 5 days. How many workmen are needed to make 105 widgets in 5 days?
(A) 7
(B) 20
(C) 25
(D) 30
(E) 60
The OA is E.
What are the calculations to solve this PS question? Experts I need help here. Thanks.
20 workmen can make 35 widgets in 5 days.
This topic has expert replies
GMAT/MBA Expert
- Brent@GMATPrepNow
- GMAT Instructor
- Posts: 16207
- Joined: Mon Dec 08, 2008 6:26 pm
- Location: Vancouver, BC
- Thanked: 5254 times
- Followed by:1268 members
- GMAT Score:770
Given: 20 workmen can make 35 widgets in 5 days.Vincen wrote:20 workmen can make 35 widgets in 5 days. How many workmen are needed to make 105 widgets in 5 days?
(A) 7
(B) 20
(C) 25
(D) 30
(E) 60
If we DOUBLE the number of workmen, then those workmen will make TWICE as many widgets in 5 days.
So, 40 workmen can make 75 widgets in 5 days.
Likewise, If we TRIPLE the number of workmen, then those workmen will make THREE TIMES as many widgets in 5 days.
So, 60 workmen can make 105 widgets in 5 days.
Answer: E
Cheers,
Brent
GMAT/MBA Expert
- [email protected]
- Elite Legendary Member
- Posts: 10392
- Joined: Sun Jun 23, 2013 6:38 pm
- Location: Palo Alto, CA
- Thanked: 2867 times
- Followed by:511 members
- GMAT Score:800
Hi Vincen,
When dealing with these types of 'work' questions, it can be helpful to think in terms of the total amount of work that needs to be done to complete the given task. We're told that it takes 20 workmen 5 days to complete the task. That's...
(20 men)(5 days each) = 100 work-days of effort to create 35 widgets.
Thus, there are a number of different ways to complete that work:
1 worker can work for 100 days
2 workers can work for 50 days each
4 workers can work for 25 days each
Etc.
The question asks us to create 105 widgets, which is 3 times the 35 in the above calculation. Those 105 widgets would take 3(100) = 300 work-days of effort. If we have to complete the job in 5 days, then we can set up the following equation:
(X men)(5 days each) = 300 work-days
X = 60 men
Final Answer: E
GMAT assassins aren't born, they're made,
Rich
When dealing with these types of 'work' questions, it can be helpful to think in terms of the total amount of work that needs to be done to complete the given task. We're told that it takes 20 workmen 5 days to complete the task. That's...
(20 men)(5 days each) = 100 work-days of effort to create 35 widgets.
Thus, there are a number of different ways to complete that work:
1 worker can work for 100 days
2 workers can work for 50 days each
4 workers can work for 25 days each
Etc.
The question asks us to create 105 widgets, which is 3 times the 35 in the above calculation. Those 105 widgets would take 3(100) = 300 work-days of effort. If we have to complete the job in 5 days, then we can set up the following equation:
(X men)(5 days each) = 300 work-days
X = 60 men
Final Answer: E
GMAT assassins aren't born, they're made,
Rich
GMAT/MBA Expert
- Jeff@TargetTestPrep
- GMAT Instructor
- Posts: 1462
- Joined: Thu Apr 09, 2015 9:34 am
- Location: New York, NY
- Thanked: 39 times
- Followed by:22 members
We are given that the rate of 20 workmen is 35/5 = 7 widgets per day. We need to determine how many workmen are needed for a rate of 105/5 = 21 widgets per day. We can let x = the number of workman and create the following proportion:Vincen wrote:20 workmen can make 35 widgets in 5 days. How many workmen are needed to make 105 widgets in 5 days?
(A) 7
(B) 20
(C) 25
(D) 30
(E) 60
20/7 = x/21
(20)(21) = 7x
(20)(3) = x
60 = x
E
Jeffrey Miller
Head of GMAT Instruction
[email protected]